Description
Previous issue was closed without completing the work. The road is still half done. The issue was not fully complete. This issue has been open for over four months. Where is the tax money going?
also asked...
Q. What road construction project are you reporting about?
A. Fosdick
A. Fosdick
Q. What is the issue?
A. Other (please use description)
A. Other (please use description)
5 Comments
Washtenaw County Road Commission (Verified Official)
Acknowledged C&D - Project Manager Mike (Verified Official)
Good Morning,
The pipe installation at Tamarack and Fosdick was completed prior to the asphalt plants
opening for the season.
We will be completing the work with Cadillac Asphalt In the next month. Please follow the progress of this work on the Weekly Projects list on our website.
An anonymous SeeClickFix user (Registered User)
An anonymous SeeClickFix user (Registered User)
Communications - Associate (Verified Official)
I have notified the foreman this area is in need to patching as we await asphalt paving. Our crews should be out there soon to perform this work.
The project manager for this paving job is still working on scheduling the asphalt paving with our contractor. As soon as we have an update, we will be sure to share with the public.