New condo project: Workers appear to have had heavy equipment in state required stream protection buffer. Construction debris also in buffer. And is fencing 25 feet from stream?
New condo project: Workers appear to have had heavy equipment in state required stream protection buffer. Construction debris also in buffer. And is fencing 25 feet from stream?
4 Komentos
Decatur Public Works - J Maximuk (Rehistradong User)
Decatur Public Works - A Hedgebeth (Beripikadong Opisiyal)
Isinara Decatur Public Works - A Hedgebeth (Beripikadong Opisiyal)
The erosion control measures are installed in the 50' buffer per the approved plans.
The subcontractor had an incident with the equipment where the tire marks are located. There was no land disturbance activity being conducted outside the limits of disturbance.
Thank you again for the information.