Deskripsyon
The contractor for long line painting has mis-marked the guides on North Ave. They have placed them on the old scrubbed out line, rather than measuring the current outer buffer line from the center line as was done the last painting cycle.
10 Komentos
Bike802 (Rehistradong User)
Kinilala DPW Pine Customer Service (Beripikadong Opisiyal)
That Guy (Rehistradong User)
Isinara Parking Services Manager (Beripikadong Opisiyal)
Due to an error in the planning process, the guide lines were mistakenly marked inside of the actual bike lane. Upon realizing the mistake, we immediately re-marked the lines based on the measurements from the original pilot project. As of Saturday 6/9, the bike lane lines have been painted according to the proper measurements.
Thank you for your interest in this project and we hope we have satisfied your request.
The Department of Public Works has resolved this request. Thanks for helping to keep Burlington a great place to live and work.