Description
Hello, just wondering if you were going to replace the grass along curb that was removed.
also asked...
Q. May I have your name and number please?
A. YES
A. YES
Q. In relation to the address/instersection where is the problem area located?
A. in front of house
A. in front of house
Q. Is it a street curb or a driveway entrance?
A. Street Curb
A. Street Curb
10 Comments
Acknowledged City of Topeka (Verified Official)
City of Topeka (Verified Official)
KD (Registered User)
City of Topeka (Verified Official)
City of Topeka (Verified Official)
City of Topeka (Verified Official)
City of Topeka Specifications for construction include the following:
• The spring seeding season is from 2/15 through 4/30
• The fall seeding season is from 8/15 through 9/30
• The Contractor is to insure a stand of healthy grass within 12 months of project acceptance.
The project was accepted as Substantially Complete on 7/1. There was seed and straw placed during construction, unfortunately during the worst time of year to establish new grass. This is often the case because of summer construction schedules.
Those areas that need additional seeding due to poor coverage will be addressed later in the summer, and if need be again next spring