Deskripsyon
Hi, I am writing to see if you will be fixing parkinson street between manning and Webster. The street was patched, but is a mess. There is also a water problem too. Thanks,
ay nagtanong din...
T. Please indicate the type of sidewalk / curb issue being reported.
S. Other
S. Other
7 Komentos
Needham, MA (Beripikadong Opisiyal)
SF (Rehistradong User)
Kinilala Highway Assistant Superintendent (Beripikadong Opisiyal)
Hello, The permit holder will be held responsible to make final repairs to the roadway. This typically occurs within 6 months after the excavation to allow for settlement. This request will be forwarded to the street opening permit inspector. The Engineering Division is reviewing the drainage issue. If you have further questions please contact the Engineering Division at 781-455-7550. Thank you,