Yem Lip (Director of Engineering)
-
Florence St Malden, MA, 02148, USA - Malden Ward 4On Florence Street from the Washington Street Intersection to Main Street, road paving is anticipated to begin Tuesday 10/27/2020. Other improvements include utility structure adjustments and wheelchair ramp adjustments on Washington Street, Ramsdell Road, and Main Street.
-
2-98 Garland Ave Malden, MA, 02148, USA - Malden Ward 1On Garland Avenue, from Judson Street to High Street, lead service line replacement (LSLR) will begin this week. Road paving is anticipated for 2021.
-
Highland Ave & Medford St Malden, MA, 02148, USA - Malden Ward 2At the intersection of Highland Avenue and Medford Street, improvements will include new pedestrian signals and push buttons; removing and replacing wheelchair ramps per requirements; and road milling, paving and line striping.
-
Cross St & Ferry St Malden, MA, 02148, USA - Malden Ward 7On Ferry Street from Cross Street to Belmont Street, lead service water line replacements (LSLR) are in progress this week. Road paving to follow.
-
Harnden Rd Malden, MA, 02148, USA - Malden Ward 2Future water main project planned for Fall 2020 - Spring 2021. Future road resurfacing and paving planned for 2022.
Limits of work: Evelyn Place to Summer Street -
Rosemont St Malden, MA, 02148, USA - Malden Ward 4Future water main project planned for August 2020.
Limits of work: Main Street to Autumn Street -
Hanover St Malden, MA, 02148, USA - Malden Ward 6Sidewalk, road resurfacing and paving planned for Fall 2020. Roadwork on hold pending Tree Hearing.
Limits of work: Eastern Avenue to Kennard Street -
Essex St Malden, MA, 02148, USA - Malden Ward 7Future wheelchair ramp work, road resurfacing and paving planned for September 2020.
Limits of work: Henry Street to Ferry Street -
Willow St Malden, MA, 02148, USA - Malden Ward 7Future water main project planned for 2021.
Limits of work: Bryant Street to Sammet Street -
Oliver St Malden, MA, 02148, USA - Malden Ward 8Future water main project planned for 2020-2021
Limits of work: Beach Street to Lynn Street -
Lincoln St Malden, MA, 02148, USA - Malden Ward 3Future water main project planned for 2020-2021.
Limits of work: Summer Street to Clifton Street. -
Evelyn Pl Malden, MA, 02148, USA - Malden Ward 2Future water main project planned for 2020-2021.
Limits of work: Pleasant Street to Harnden Road -
Chestnut St Malden, MA, 02148, USA - Malden Ward 3Future water main project planned for 2020-2021.
Limits of work: Cedar Street to Summer Street. -
Emerald St Malden, MA, 02148, USA - Malden Ward 2
Substantially completed lead service line replacement work.
Limits of work: Pearl Street to Highland Avenue
-
Webber St Malden, MA, 02148, USA - Malden Ward 6
Substantially completed work, including installation of new water main, gate valve, and hydrant.
Limits of work: Lebanon Street to Valley Street
-
Olive Ave Malden, MA, 02148, USA - Malden Ward 6Limits of work: Rockingham Avenue to Beachview Street