Mô tả
INSTALL: NEW CROSSWALK TO STANDARD WITH SIGNS. PAVEMENT WILL NEED TO BE CORRECTED AT CURB LINES FOR DRAINAGE, UPGRADE RAMPS TO ADA REQUIREMENTS, RELOCATE SPEED LIMIT SIGNAGE. (SEE ATTACHED PHOTO)
PER MIKE FREDERICK, WORK NEEDS TO BE COMPLETED BY AUGUST 1, 2019
cũng đã hỏi...
Hỏi. What work is being requested?
Đáp. Markings
Đáp. Markings
4 Bình luậns
Neighborhood Transportation Assistant (Chính thức đã xác nhận)
Được thừa nhận Stormwater Pavement & Traffic Special Projects Manager (Người dùng đã đăng ký)
Thank you, request is acknowledged. Please be advised due to other scheduled projects, this project can not be guaranteed complete by August 1, 2019. It is scheduled. If you have any questions, please contact SPTO Construction at 727-892-5546.
Thank you,
TSmith
MWoodley (Người dùng đã đăng ký)
Đã đóng MWoodley (Người dùng đã đăng ký)
MW, wt
Wo#5978i