说明
INSTALL: NEW CROSSWALK TO STANDARD WITH SIGNS. PAVEMENT WILL NEED TO BE CORRECTED AT CURB LINES FOR DRAINAGE, UPGRADE RAMPS TO ADA REQUIREMENTS, RELOCATE SPEED LIMIT SIGNAGE. (SEE ATTACHED PHOTO)
PER MIKE FREDERICK, WORK NEEDS TO BE COMPLETED BY AUGUST 1, 2019
还问了...
问 What work is being requested?
答 Markings
答 Markings
4 评论s
Neighborhood Transportation Assistant (官方验证)
已确认 Stormwater Pavement & Traffic Special Projects Manager (注册用户)
Thank you, request is acknowledged. Please be advised due to other scheduled projects, this project can not be guaranteed complete by August 1, 2019. It is scheduled. If you have any questions, please contact SPTO Construction at 727-892-5546.
Thank you,
TSmith
MWoodley (注册用户)
关闭 MWoodley (注册用户)
MW, wt
Wo#5978i