Descripción
This stretch of the sidewalk (half of the block) has been torn up for months, and the pedestrian's right of way is completely gone. The city's contractor must restore the concrete or at least fill the holes with temporary asphalt. Pedestrians are forced to step into busy street traffic to pass this large zone—an unsafe condition for pedestrians and drivers alike.
también preguntó...
Q. What is the area of your concern?
A. Other - Restoration Due to Utility Work.
A. Other - Restoration Due to Utility Work.
Q. Adjacent Property Type?
A. Business
A. Business
3 Comentars
Reconocido City of Houston 311 (Oficial verificado)
Amanda (Usuario registrado)
Cerrado City of Houston 311 (Oficial verificado)
Service Request Resolved
Concrete supervisor made multiple site visit for sidewalk restoration. Per him, as of 02/04/2016, Gas company still on site doing project. Sidewalk need to be on hold untill gas company finish the project. Refer to wo# 12502381.