Description
Work is continuing on the raised intersection at Orange and Audubon. Phase 1 has been completed, and phase 2 will continue next week. Phase 3's previously scheduled closure for tomorrow has been postponed to the following Saturday of 10/13/18.
Phase 1: Work on the west side of the Orange Street has been completed.
Phase 2: Work on the east side of the Orange Street will be done with one lane open in each direction on Orange Street and one lane open on Audubon Street between Whitney and Orange and Audubon Street closed east of the intersection. Access to Audubon Street east of Orange will be from State Street, and Audubon will operate with two way traffic in that block. Parking will be prohibited.
Phase 3: On Saturday, 10/13, Orange Street will be closed between Grove and Trumbull for final paving.
Thank you for your continuing patience in this matter.
1 Comment
Closed Manager of Operations, Process Improvement - Transportation, Traffic, & Parking (Verified Official)
https://seeclickfix.com/issues/5014752