Update on schedule for skating rink? Contractors are working a few days every few weeks. When is the expected completion date ?
Update on schedule for skating rink? Contractors are working a few days every few weeks. When is the expected completion date ?
3 Comments
MNHGA (Registered User)
Acknowledged Rebecca Bombero, Deputy Chief Administrative Officer (Verified Official)
We are still on track for completion of Phase I improvements - the extended roof to allow regulation size ice, new slab and cooling system and working bathrooms - for late 2018.
Phase II improvements which will include a renovated warming hut, new locker rooms, concessions, pro shop and improved parking are slated for completion in Fall 2019.